Owner

Wastewater Treatment Plant Phase 1A Expansion

Engineer

CH2MHill

Objective


Revamp the aging Olivehurst wastewater treatment plant and add significant capacity plus title 22 compliance with cloth disc filtration and ultraviolent disinfection.

Challenge


Placing over 9,000 cubic yards of concrete constructing over 4 million gallons of tankage with Western Water crews peaking at 40 workers in addition to multiple subcontractors.

Result


Process and treat the District’s wastewater to Title 22 standards allowing reuse as irrigation water for the neighboring communities.